Engineering – Project Management - Pumps

Ti West – Cooljarloo - Murchison, Western Australia

Staged Transfer of Slurry

The client needed assistance with the staged transfer of slurry. NPE had the people, products and experience to deliver on brief.

Silica sand slurry (460lt/sec @ 30m TDH) was transferred utilising seven staged pumps. NPE designed, created, installed and commissioned the system in June 2009 and has an ongoing contract for work on this project.

Requirements

To transfer silica sand slurry (460lt/sec @ 30m TDH) utilising seven staged pumps.

Equipment

  • 22,000v – 415v 500kw Electric warman slurry pumps
  • 22,000v remote pole top cable connections
  • Back to base monitoring and start/stop control
  • Synchromesh belt drive for increased reliability and reduced servicing schedules

National Pump & Energy have the people, products and expertise to deliver on your project needs. For more information contact us today.