Critical Confined Space Bypass, VIC

NPE were engaged in cleaning out & inspecting a man-hole.

The task was complicated as the job was located in a residential area, requiring street closures and sound restraints. The project was monitored 24/7 for three days.

The project’s bypass depths were 29m. It required a crane man box to lower personnel into the sewer to be able to pressure wash & clean it out.

NPE supplied a flow management plan which included installing bypass pumps, and we were required to set up a sewer bypass for two man-holes.

This critical bypass project was completed with 0 incidents, on time and within budget.

NPE has a huge range of hire pump and power equipment for bypass works, with all equipment in stock and ready to deploy to your site.

Watch our Project Video here

Critical Confined Space Bypass, VIC

Requirements, Equipment and Images

Get in touch to discuss your requirements...

Call Us

NPE has not only one of the largest ranges of specialised equipment, but also the most qualified professionals in pumping and power generation in Australia.

Visit A Location

The NPE branch network is strategically positioned to service all parts of Australia. These hire branches are supported by a team of NPE representatives and field service crews.

© National Pump & Energy 2024

Website created by RJ New Designs