Well Point Dewatering, Perth WA

NPE were engaged by Alita Constructions to install dewatering at 2 different locations at their project located on Dowd St, Welshpool.

The purpose of the install was to allow the client to excavate below the water table to complete the final connection of the site stormwater system and install a large aerobic treatment unit.

We had our dewatering pumps and equipment delivered to site, the systems installed and running within 48 hours! The job ran for most of the week.

The client was really happy and the job was completed safely, and in a timely manner.

PFAS Treatment Perth, WA

The treatment process begins with a dewatering system that extracts groundwater for processing. The influent is conveyed through the plant,…

Read More

Critical Sewer Bypass Solution with Dual Diesel Pump System

National Pump & Energy (NPE) was engaged to support a critical infrastructure project with a temporary sewer bypass solution. The…

Read More

Bypass Pumping Solution at Boundary Creek

National Pump & Energy (NPE) was engaged by the Water Corporation’s Water Resource Development Team (WRDT) to implement a robust…

Read More

Creek Bypass & Dewatering Success at Mullet Creek

When D4C began infrastructure works at Mullet Creek, they faced complex water management challenges including maintaining creek flow, controlling groundwater…

Read More

Wellpoint Dewatering System Rottnest Island

Compact Wellpoint Dewatering System Delivered for Rottnest Island WWPS Project NPE recently delivered a compact wellpoint dewatering system for a…

Read More

NPE Doubles the Impact

We’re excited to announce that NPE has pledged to match every dollar we raise-up to $5,000-if we reach our fundraising…

Read More

West Dapto Dewatering & Water Treatment NSW

NPE is supporting critical sewer and water infrastructure works at West Dapto, the fastest-growing residential area in NSW outside Sydney,…

Read More