Student Accommodation Development – NSW
Student Accommodation Development
Dewatering was required to allow for the construction of student accommodation with a 2-level basement car park. Bulk excavation level approx. 5m BEGL with localised pits going further 1.5m deep to 6.5m BEGL.
Installation of 240m perimeter dewatering system along with localised pit dewatering. Treatment to ANZEC 95% Freshwater guidelines.
The Chemical Dosing System installation was recommended for efficient water clarification and pH correction. The system is designed to effectively remove silt, sand, and other solids from water at flow rates of up to 5L/s. This makes it an excellent choice for sites with limited space. The system incorporates the addition of flocculants, coagulants, and pH adjustments throughout the treatment process. It also includes monitoring features such as pH, turbidity, and flow meter measurements. The final step of the treatment process at Richards Crookes involves the use of a metals removal module (MRM) for oxidation and filtration, specifically targeting elevated metal concentrations in the water.
Richard Crookes site encounters the presence of heavy metals in its groundwater, including Aluminium, Arsenic, Zinc, Manganese, and Iron. These heavy metals pose a challenge for the project and NPE is committed to meeting the ANZECC & ARMCANZ (2000) freshwater quality guidelines.
NPE chooses the most suitable chemical compositions to treat the water and activates and cleans MRM media to ensure maximum media efficiency.
NSW Central Coast Sewer Bypass Upgrade
National Pump & Energy was engaged to design, supply, install, and maintain a temporary sewer bypass pumping system to support…
Jovan Qualifies as Mechanical Fitter in Newcastle NSW | Apprenticeship Success
We are proud to announce that Jovan has officially qualified as a Mechanical Fitter after successfully completing his apprenticeship at…
Proud Entertainment Sponsor of the CCFWA Awards Night 2026
The CCFWA Awards Night 2026 was a fantastic evening celebrating excellence across Western Australia’s civil construction industry. We were proud…
Residential Development Dewatering & Water Treatment – Calderwood, NSW
Building on the success of long-term dewatering and water treatment works in the Illawarra region, National Pump & Energy (NPE)…
Jack Achieves Tradesman Qualification at NPE Perth Branch in Western Australia
We are proud to announce that Jack has officially qualified as a Tradesman after successfully completing his apprenticeship at NPE…
Restart Ready: Delivering Critical Pontoon Pumping Power in Queensland
National Pump and Energy (NPE) are the industry-leading Water Management and Treatment Solutions experts. Offering Dewatering, Bypass Pumping, Pump Hire…
Large-Scale Evaporation for TSF Risk Reduction
Our client required a 24-unit evaporator fan package at a North-West Queensland Mine site to lower water levels within the…