Wellpoint Dewatering System for our client in Goolwa, SA

NPE installed a Wellpoint Dewatering System for our client in Goolwa.
Our client was laying sewer for new development when they discovered groundwater 1m to 1.8m below ground level.

NPE installed a 50m system to a depth of 6m to ensure groundwater was lowered beneath their 3.6m invert.

This system worked flawlessly and was operational for one week.

Wet Season Management in North-West Queensland Mining​

NPE was engaged to support a remote north-west Queensland operation following significant rainfall, with approximately 370 mm recorded over a…

Royal Far West Manly Dewatering

NPE was awarded a dewatering and water treatment project to facilitate construction activities. To manage this project effectively, the temporary…

PFAS Treatment Perth, WA

The treatment process begins with a dewatering system that extracts groundwater for processing. The influent is conveyed through the plant,…

Critical Sewer Bypass Solution with Dual Diesel Pump System

National Pump & Energy (NPE) was engaged to support a critical infrastructure project with a temporary sewer bypass solution. The…

Bypass Pumping Solution at Boundary Creek

National Pump & Energy (NPE) was engaged by the Water Corporation’s Water Resource Development Team (WRDT) to implement a robust…

Creek Bypass & Dewatering Success at Mullet Creek

When D4C began infrastructure works at Mullet Creek, they faced complex water management challenges including maintaining creek flow, controlling groundwater…

Wellpoint Dewatering System Rottnest Island

Compact Wellpoint Dewatering System Delivered for Rottnest Island WWPS Project NPE recently delivered a compact wellpoint dewatering system for a…