Sewage Bypass, 18m Deep Manhole – Victoria

NPE were engaged in managing and constructing a sewer bypass for new sewer connections works to be carried out in a 10-day operation.

Our Melbourne team are the leading provider in bypass pumping. We deliver the complete bypass solution. With flow management plans, Telemetry displays full visibility on critical pumping performance values & flow, pumping and pipeline and installation, all manned 24/7.

Meeting our client’s standards and requirements with the management, resources, and capabilities to deliver the overall project objectives, including the following:

  • Pumping & Pipeline Installation completion within the client’s timeframe
  • Thorough testing of all equipment, pipelines and all site works for the project before commencement
  • The performance of the project works in a safe and environmentally responsible manner
  • Provide access to our clients and key stakeholder personnel to inspect, monitor and audit the works in progress
  • Maintain appropriate safety, environmental and quality control measure at all times

Wet Season Management in North-West Queensland Mining​

NPE was engaged to support a remote north-west Queensland operation following significant rainfall, with approximately 370 mm recorded over a…

Royal Far West Manly Dewatering

NPE was awarded a dewatering and water treatment project to facilitate construction activities. To manage this project effectively, the temporary…

PFAS Treatment Perth, WA

The treatment process begins with a dewatering system that extracts groundwater for processing. The influent is conveyed through the plant,…

Critical Sewer Bypass Solution with Dual Diesel Pump System

National Pump & Energy (NPE) was engaged to support a critical infrastructure project with a temporary sewer bypass solution. The…

Bypass Pumping Solution at Boundary Creek

National Pump & Energy (NPE) was engaged by the Water Corporation’s Water Resource Development Team (WRDT) to implement a robust…

Creek Bypass & Dewatering Success at Mullet Creek

When D4C began infrastructure works at Mullet Creek, they faced complex water management challenges including maintaining creek flow, controlling groundwater…

Wellpoint Dewatering System Rottnest Island

Compact Wellpoint Dewatering System Delivered for Rottnest Island WWPS Project NPE recently delivered a compact wellpoint dewatering system for a…