Screening Solution, Sewage Treatment Plant – Byron Bay NSW
NPE was asked to provide a screening solution that would allow the local council to take their entire inlet works offline for an extended period to facilitate the strip out, re-coating and refurbishment of their inlet works at the Byron Bay sewage treatment plant.
The solution required the sewage treatment plant to be operational 24/7 and the bioreactor and treatment processes to be maintained without risking further damage to the facility or its systems; this work was declared essential and critical.
NPE designed, fabricated and installed a screening and bypass solution that could cater for complete redundancy and allow the inlet works to be taken offline indefinitely whilst the urgent works were completed.
The inlet works on-site were fed by 4 individual rising mains that delivered the entire town of Byron Bay’s wastewater supply to the plant for treatment. It was imperative that the solution proposed by NPE had built-in redundancy and provided a level of screening that would allow the plant to continue under normal operations whilst the inlet works were offline. Wet weather contingency was another major consideration within the design of NPE’s temporary screening system. We needed to ensure that not only was the system capable of managing the peak incoming flows to the plant with redundancy but that it could also manage prolonged spikes from wet weather flows on the back of localised storms and periods of heavy rain.
Wellpoint Dewatering Solution Delivered for Modcon Civil- SA
Our South Australian team was recently engaged by Modcon Civil to design and deliver a tailored dewatering solution in Robe,…
Eastern Treatment Plant Bypass – Melbourne, VIC
National Pump & Energy deliver bypass works for the incoming side of one of Melbourne’s busiest treatment plants. Eastern Treatment…
Bore Pump Installations & Commissioning – Kalgoorlie WA
The Kalgoorlie branch has recently completed a large run of bore pump installations and commissioning works across several sites. Over…
DN630 Pipeline Welding & Installation Project – Queensland
National Pump & Energy (NPE) was engaged to deliver specialised support for a DN630 HDPE pipeline installation as part of…
Poly Butt Welding for Resource Recovery Park
National Pump & Energy (NPE) was engaged to supply experienced poly welders and specialist poly welding equipment to support onsite…
NSW Central Coast Sewer Bypass Upgrade
National Pump & Energy was engaged to design, supply, install, and maintain a temporary sewer bypass pumping system to support…
Jovan Qualifies as Mechanical Fitter in Newcastle NSW | Apprenticeship Success
We are proud to announce that Jovan has officially qualified as a Mechanical Fitter after successfully completing his apprenticeship at…




