Belconnen Trunk Sewer Augmentation – ACT

NPE were engaged to perform a critical bypass required in order for our client to complete the final stage of a major project building additional capacity and redundancy into the local water authorities wastewater network. NPE’s role was to install, commission and manage the sewer via a pumped overland bypass in order to provide a dry double isolated pipeline that would allow our client to complete their tie works. The window for installation and completion of the works was extremely tight. Access was difficult as the alignment ran parallel to a major roadway where the pipe alignment snaked through a sensitive green site where disturbance to the local flora was to be kept to a minimum.

NPE designed a sewer bypass system where we supplied 4 x BA300E pumps to ensure that the nominated PDWF rate of 650 l/s with 100% redundancy could easily be achieved whilst still providing additional capacity to meet higher PWWF that were likely to be encountered during the tight project timeline due to the stormy and unpredictable wet weather the area had been receiving.

Due to the critical nature of the project and tight time frames of operation, NPE provided 24/7 on-site monitoring in conjunction with the telemetry system to ensure that the risk of overflow was removed in the event of ramping the bypass up to cater for PWWF due to the shallow collection manhole for the bypass and presence of an overflow point upstream which meant levels within the bypass collection manhole had to be kept to a minimum at all times.

Wellpoint Dewatering Solution Delivered for Modcon Civil- SA

Our South Australian team was recently engaged by Modcon Civil to design and deliver a tailored dewatering solution in Robe,…

Eastern Treatment Plant Bypass – Melbourne, VIC

National Pump & Energy deliver bypass works for the incoming side of one of Melbourne’s busiest treatment plants. Eastern Treatment…

Bore Pump Installations & Commissioning – Kalgoorlie WA

The Kalgoorlie branch has recently completed a large run of bore pump installations and commissioning works across several sites. Over…

DN630 Pipeline Welding & Installation Project – Queensland

National Pump & Energy (NPE) was engaged to deliver specialised support for a DN630 HDPE pipeline installation as part of…

Poly Butt Welding for Resource Recovery Park

National Pump & Energy (NPE) was engaged to supply experienced poly welders and specialist poly welding equipment to support onsite…

NSW Central Coast Sewer Bypass Upgrade

National Pump & Energy was engaged to design, supply, install, and maintain a temporary sewer bypass pumping system to support…

Jovan Qualifies as Mechanical Fitter in Newcastle NSW | Apprenticeship Success

We are proud to announce that Jovan has officially qualified as a Mechanical Fitter after successfully completing his apprenticeship at…