Dewatering for Brown Plumbing & Civil in Southern River, Perth
NPE was approached in late 2022 by our client Brown Plumbing & Civil regarding dewatering that was required for the installation of a new sewer pipe via the Micro Tunnelling drilling method due to the existing sewer pipe had been compromised, leaving some residents without working sewage in Southern River, Perth.
The Jacking and Receival drill pits had invert depths of up to 4.5m from GL (ground level); therefore, each required a temporary aquifer drawdown of 3m from static water table level to achieve adequate cone of depression. NPE provided complete coverage over this project, starting with the dewatering methodology proposal, followed by all the pre-dewatering requirements managed by our environmental team, which included: The installation of monitoring wells via Direct Push Probing Soil and groundwater sampling for lab analysis Disposal option and treatment operation strategy for dewatering discharge effluent.
Consulting with local city/councils for approval to discharge dewatering effluent into a large infiltration swale near Conservation Wetlands Discharge applications for sewer chamber use to Water Authorities (Water Corporation) Upon NPE being granted the discharge approval for Brown Plumbing & Civil, legislative set eco system criteria were to be adhered to throughout this project dewatering duration, which was followed strictly by implementing all water treatment and environmental requirements accordingly via dosing units, clarifiers, daily field water sampling & weekly lab sampling. Also included were the approval conditions with flow rate and infiltration swale capacity not to be exceeded. This was compiled into the detailed Closure Report submitted to the City/Council’s governing bodies at project completion.
Given the sensitivity of the existing compromised sewer pipe, this project start date was pushed out 12 months from the initial RFQ. All dewatering operations installed by our AIC went exceptionally well, providing dry ground conditions for the Micro Tunnelling equipment and civil plumbers to complete their new sewer connections. AIC established additional sound attenuation to support the silenced canopy dewatering pumps, providing an even lower dB noise reduction for the residential location of these drill pits. Working alongside Brown Plumbing & Civil again and completing NPE’s scope across these drill and receival pits with no problems was a great pleasure.
Critical Sewer Bypass Solution with Dual Diesel Pump System
National Pump & Energy (NPE) was engaged to support a critical infrastructure project with a temporary sewer bypass solution. The…
Read MoreBypass Pumping Solution at Boundary Creek
National Pump & Energy (NPE) was engaged by the Water Corporation’s Water Resource Development Team (WRDT) to implement a robust…
Read MoreCreek Bypass & Dewatering Success at Mullet Creek
When D4C began infrastructure works at Mullet Creek, they faced complex water management challenges including maintaining creek flow, controlling groundwater…
Read MoreWellpoint Dewatering System Rottnest Island
Compact Wellpoint Dewatering System Delivered for Rottnest Island WWPS Project NPE recently delivered a compact wellpoint dewatering system for a…
Read MoreNPE Doubles the Impact
We’re excited to announce that NPE has pledged to match every dollar we raise-up to $5,000-if we reach our fundraising…
Read MoreWest Dapto Dewatering & Water Treatment NSW
NPE is supporting critical sewer and water infrastructure works at West Dapto, the fastest-growing residential area in NSW outside Sydney,…
Read MoreNPE Shines at NT Resources Week 2025
National Pump & Energy (NPE) was proud to exhibit at NT Resources Week 2025 in Darwin, showcasing our cutting-edge pumping,…
Read More