We were engaged by BOS Civil, which required prompt dewatering in troublesome ground conditions throughout their 2 x extensive basin excavation works in Balcatta, WA. 

The following morning, NPE mobilised all plant and technician specialists to start the wellpoint installation. The ground’s existing building materials, including rubble, bricks, steel, car diffs, and other obstructions, became apparent during wellpoint attempts, and this caused us to rethink and change our installation approach.

To ensure we could achieve the required invert depth, NPE provided an alternative wellpoint installation solution allowing the wells to stay open for the installation of each spear, maintaining absolute screen coverage of the gravel pack. 

NPE also provided a localised sump pumping method staged across the areas as needed, which was sent into the dewatering discharge lines and all boosted approximately 200m away from the designated on-site infiltration basin. This was done because the actual ground soils also contained peat layers that were about 4-5 metres deep. 

This job was a great success and provided a fantastic opportunity to utilise NPE’s specialist knowledge when up against unforeseen challenges.

West Dapto Dewatering & Water Treatment NSW

NPE is supporting critical sewer and water infrastructure works at West Dapto, the fastest-growing residential area in NSW outside Sydney,…

Read More

NPE Shines at NT Resources Week 2025

National Pump & Energy (NPE) was proud to exhibit at NT Resources Week 2025 in Darwin, showcasing our cutting-edge pumping,…

Read More

EnviroPacific: Former PDP2 Oily Wastewater Pond Remediation

NPE was contracted to undertake the design, installation and operation of the dewatering system for this project. The NPE inhouse…

Read More

Broadbeach Dewatering & Water Treatment QLD

Iris Built has undertaken to build a monumental construction project on Broadbeach, Victoria & Albert. As part of this, the…

Read More

Alkimos Seawater Desalination Plant Perth, WA

The Alkimos Seawater Desalination Plant (ASDP) – Stage 1 is a major infrastructure initiative aimed at delivering 50 gigalitres per…

Read More

Sewer Bypass of Naracoorte WWTP. Naracoorte SA

NPE were engaged to bypass the entire inflow to the Naracoorte WWTP whilst the clients existing Pump and Power infrastructure…

Read More

Dewatering Rustlers Roost

NPE Darwin offering dewatering packages in preparation for the 3 billion litres of water that will hit the top end…

Read More