Bypass Solutions, Monbulk VIC
NPE was engaged to supply a potable water bypass pumping system, while the existing Monbulk pump station at Silvan Reservoir was receiving a major structural overhaul and new pumps.
In conjunction with AMS and Melbourne Water, a bypass system was designed to be able to confidently take the existing pump station offline for an extended period with confidence that the local community would receive potable drinking water for the duration of the project.
NPE custom made medium head electric centrifugal pumps to suit the duty required to utilise the mains power on site from the decommissioned pump station while works were being undertaken. NPE pump station was positively fed through a 400m long 450mm poly pipeline connected to the Upper Yarra to Silvan pipeline, bypassing the Monbulk Pump Station. This water was then pumped through the water treatment plant up to the McCarthy Road tanks to supply the local area with potable drinking water.
Switching over pumpstations from the Cardinia to the NPE bypass had a narrow window to perform and had to be completed within the same shift. The existing Monbulk pumpstation had to first be disconnected, electrically and operationally to supply the NPE bypass the power and operation through the Melbourne Water network. To add complexity the final discharge point for NPE to connect into the existing pipeline, had to be cut in on the same day as the electrical and instrumentation works.
General pump operation was through the SCADA network as it was integrated with the water treatment plant and tank level. On top of this NPE had our own secondary, independent telemetry to alert of any faults and monitor pump performance, with remote access ability if it was ever required.
If you need more information about this project or want to discuss potential collaborations, please reach out to us today!
West Dapto Dewatering & Water Treatment NSW
NPE is supporting critical sewer and water infrastructure works at West Dapto, the fastest-growing residential area in NSW outside Sydney,…
Read MoreNPE Shines at NT Resources Week 2025
National Pump & Energy (NPE) was proud to exhibit at NT Resources Week 2025 in Darwin, showcasing our cutting-edge pumping,…
Read MoreEnviroPacific: Former PDP2 Oily Wastewater Pond Remediation
NPE was contracted to undertake the design, installation and operation of the dewatering system for this project. The NPE inhouse…
Read MoreBroadbeach Dewatering & Water Treatment QLD
Iris Built has undertaken to build a monumental construction project on Broadbeach, Victoria & Albert. As part of this, the…
Read MoreAlkimos Seawater Desalination Plant Perth, WA
The Alkimos Seawater Desalination Plant (ASDP) – Stage 1 is a major infrastructure initiative aimed at delivering 50 gigalitres per…
Read MoreSewer Bypass of Naracoorte WWTP. Naracoorte SA
NPE were engaged to bypass the entire inflow to the Naracoorte WWTP whilst the clients existing Pump and Power infrastructure…
Read MoreDewatering Rustlers Roost
NPE Darwin offering dewatering packages in preparation for the 3 billion litres of water that will hit the top end…