Tank Flush, Esperance WA

NPE were engaged by Carey MC to provide Dewatering and Environmental Management for the Berth 2 hardstand renewal, construction of flush tanks and installation of a dissolved metal treatment filter system at Southern Ports’ Port of Esperance.

NPE began with the development of the Dewatering Management Plan to align with the conditions required by the Southern Ports Authority.

After strict security checks (MSIC) and inductions NPE mobilised the personnel, drilling equipment and dewatering equipment to the Esperance Port on the 23rd of January.

The Guys on site did a great job drilling 5 production bores, 1 x monitoring well and installing the pumps, generators, flow meters and the poly ring main. They operated on a very tight time frame which allowed Carey MC to return to the original schedule after losing time during the piling due to difficult ground conditions.

NPE achieved the adequate draw down which allowed Carey MC to excavate down to invert. The concrete blinding has been poured and the first base slab is due to be poured in the coming days. The excavation ( supported by sheet piles) is approximately 12m x 14m x 7m deep. The current groundwater draw down is around 5m allowing sufficient compaction and dry working conditions.

NPE Continue to monitor the dewatering and environmental quality with weekly lab samples and on site testing every other day. The dewatering is scheduled to run for a total of 10-12 weeks.

The personnel on site have received great feedback from Carey MC.

Wellpoint Dewatering Solution Delivered for Modcon Civil- SA

Our South Australian team was recently engaged by Modcon Civil to design and deliver a tailored dewatering solution in Robe,…

Eastern Treatment Plant Bypass – Melbourne, VIC

National Pump & Energy deliver bypass works for the incoming side of one of Melbourne’s busiest treatment plants. Eastern Treatment…

Bore Pump Installations & Commissioning – Kalgoorlie WA

The Kalgoorlie branch has recently completed a large run of bore pump installations and commissioning works across several sites. Over…

DN630 Pipeline Welding & Installation Project – Queensland

National Pump & Energy (NPE) was engaged to deliver specialised support for a DN630 HDPE pipeline installation as part of…

Poly Butt Welding for Resource Recovery Park

National Pump & Energy (NPE) was engaged to supply experienced poly welders and specialist poly welding equipment to support onsite…

NSW Central Coast Sewer Bypass Upgrade

National Pump & Energy was engaged to design, supply, install, and maintain a temporary sewer bypass pumping system to support…

Jovan Qualifies as Mechanical Fitter in Newcastle NSW | Apprenticeship Success

We are proud to announce that Jovan has officially qualified as a Mechanical Fitter after successfully completing his apprenticeship at…