Pump Station Bypass – Queensland

A local water authority recently asked NPE to provide a bypass for a pump station, the pump station needed to be taken offline to complete works.

The bypass needed to be capable of 75L/S, this was diverting flow from a DN900 line.

NPE mobilised the necessary pumps & pipework (200m) in a prompt manner delivering an effective solution as per the client’s needs. All discharge pipework (HDPE) was supplied and welded on-site to suit.

This bypass’s technical component was to achieve double isolation on the existing pipework. NPE was able to complete confined space entries into a 13m deep manhole safely to achieve this.

NPE included remote telemetry monitoring, providing a clear picture of the network’s equipment status and fluid level.

The weather was challenging, as 25mm of rain fell the night the system was commissioned. This had a significant impact on the network, but the pumping solution provided was able to handle the increased flow without surcharging or spilling.

Powering Remote Mining Operations with Reliable Off-Grid Energy

National Pump & Energy was engaged to deliver and commission a complete remote power solution to support critical underground services…

Sewer Treatment Plant Wellpoint Dewatering – NSW

National Pump & Energy (NPE) was engaged to provide a wellpoint dewatering solution for the construction of two new clarifiers…

Pipeline Dewatering Specialists: Wellpoint Installation for Belmont Infrastructure Project

As part of a 6km pipeline installation project in Belmont, our client successfully completed almost the entire pipeline without requiring…

Wellpoint Dewatering Solution Delivered for Modcon Civil- SA

Our South Australian team was recently engaged by Modcon Civil to design and deliver a tailored dewatering solution in Robe,…

Eastern Treatment Plant Bypass – Melbourne, VIC

National Pump & Energy deliver bypass works for the incoming side of one of Melbourne’s busiest treatment plants. Eastern Treatment…

Bore Pump Installations & Commissioning – Kalgoorlie WA

The Kalgoorlie branch has recently completed a large run of bore pump installations and commissioning works across several sites. Over…

DN630 Pipeline Welding & Installation Project – Queensland

National Pump & Energy (NPE) was engaged to deliver specialised support for a DN630 HDPE pipeline installation as part of…