Pump Station Bypass – Queensland
A local water authority recently asked NPE to provide a bypass for a pump station, the pump station needed to be taken offline to complete works.
The bypass needed to be capable of 75L/S, this was diverting flow from a DN900 line.
NPE mobilised the necessary pumps & pipework (200m) in a prompt manner delivering an effective solution as per the client’s needs. All discharge pipework (HDPE) was supplied and welded on-site to suit.
This bypass’s technical component was to achieve double isolation on the existing pipework. NPE was able to complete confined space entries into a 13m deep manhole safely to achieve this.
NPE included remote telemetry monitoring, providing a clear picture of the network’s equipment status and fluid level.
The weather was challenging, as 25mm of rain fell the night the system was commissioned. This had a significant impact on the network, but the pumping solution provided was able to handle the increased flow without surcharging or spilling.
Powering Remote Mining Operations with Reliable Off-Grid Energy
National Pump & Energy was engaged to deliver and commission a complete remote power solution to support critical underground services…
Sewer Treatment Plant Wellpoint Dewatering – NSW
National Pump & Energy (NPE) was engaged to provide a wellpoint dewatering solution for the construction of two new clarifiers…
Pipeline Dewatering Specialists: Wellpoint Installation for Belmont Infrastructure Project
As part of a 6km pipeline installation project in Belmont, our client successfully completed almost the entire pipeline without requiring…
Wellpoint Dewatering Solution Delivered for Modcon Civil- SA
Our South Australian team was recently engaged by Modcon Civil to design and deliver a tailored dewatering solution in Robe,…
Eastern Treatment Plant Bypass – Melbourne, VIC
National Pump & Energy deliver bypass works for the incoming side of one of Melbourne’s busiest treatment plants. Eastern Treatment…
Bore Pump Installations & Commissioning – Kalgoorlie WA
The Kalgoorlie branch has recently completed a large run of bore pump installations and commissioning works across several sites. Over…
DN630 Pipeline Welding & Installation Project – Queensland
National Pump & Energy (NPE) was engaged to deliver specialised support for a DN630 HDPE pipeline installation as part of…