Hydromining – Koolan Iron Ore, WA

To expand the storage capacity of the Sediment Pond at Koolan Island, NPE were engaged to undertake a Hydromining campaign to remove approximately 3,600m3 of settled solids.

NPE used a high-pressure water technique to break down the compacted material into a slurry via water sourced from three Hydromining cannons on the sediment pond’s external perimeter.

The cannons pushed/moved the slurry product to a Hydraulic Pump, suspended in the pond with a crane. The slurry was pumped through a discharge line into a newly constructed sump. The water necessary for the cannons was supplied by a high-pressure diesel-driven pump.

The HP pump was connected to a break tank, supplied with water from the in-pit dewatering system. The estimated flow rate required for the high-pressure pump and cannons was approximately 55 litres per second.

NPE provided three on-site operational personnel to undertake the project. Each shift was led by an experienced NPE-trained Hydromining Supervisor with two Field Technicians supporting.

Wellpoint Dewatering Solution Delivered for Modcon Civil- SA

Our South Australian team was recently engaged by Modcon Civil to design and deliver a tailored dewatering solution in Robe,…

Eastern Treatment Plant Bypass – Melbourne, VIC

National Pump & Energy deliver bypass works for the incoming side of one of Melbourne’s busiest treatment plants. Eastern Treatment…

Bore Pump Installations & Commissioning – Kalgoorlie WA

The Kalgoorlie branch has recently completed a large run of bore pump installations and commissioning works across several sites. Over…

DN630 Pipeline Welding & Installation Project – Queensland

National Pump & Energy (NPE) was engaged to deliver specialised support for a DN630 HDPE pipeline installation as part of…

Poly Butt Welding for Resource Recovery Park

National Pump & Energy (NPE) was engaged to supply experienced poly welders and specialist poly welding equipment to support onsite…

NSW Central Coast Sewer Bypass Upgrade

National Pump & Energy was engaged to design, supply, install, and maintain a temporary sewer bypass pumping system to support…

Jovan Qualifies as Mechanical Fitter in Newcastle NSW | Apprenticeship Success

We are proud to announce that Jovan has officially qualified as a Mechanical Fitter after successfully completing his apprenticeship at…