Hydromining – Koolan Iron Ore, WA
To expand the storage capacity of the Sediment Pond at Koolan Island, NPE were engaged to undertake a Hydromining campaign to remove approximately 3,600m3 of settled solids.
NPE used a high-pressure water technique to break down the compacted material into a slurry via water sourced from three Hydromining cannons on the sediment pond’s external perimeter.
The cannons pushed/moved the slurry product to a Hydraulic Pump, suspended in the pond with a crane. The slurry was pumped through a discharge line into a newly constructed sump. The water necessary for the cannons was supplied by a high-pressure diesel-driven pump.
The HP pump was connected to a break tank, supplied with water from the in-pit dewatering system. The estimated flow rate required for the high-pressure pump and cannons was approximately 55 litres per second.
NPE provided three on-site operational personnel to undertake the project. Each shift was led by an experienced NPE-trained Hydromining Supervisor with two Field Technicians supporting.
Sewer Treatment Plant Wellpoint Dewatering – NSW
National Pump & Energy (NPE) was engaged to provide a wellpoint dewatering solution for the construction of two new clarifiers…
Pipeline Dewatering Specialists: Wellpoint Installation for Belmont Infrastructure Project
As part of a 6km pipeline installation project in Belmont, our client successfully completed almost the entire pipeline without requiring…
Wellpoint Dewatering Solution Delivered for Modcon Civil- SA
Our South Australian team was recently engaged by Modcon Civil to design and deliver a tailored dewatering solution in Robe,…
Eastern Treatment Plant Bypass – Melbourne, VIC
National Pump & Energy deliver bypass works for the incoming side of one of Melbourne’s busiest treatment plants. Eastern Treatment…
Bore Pump Installations & Commissioning – Kalgoorlie WA
The Kalgoorlie branch has recently completed a large run of bore pump installations and commissioning works across several sites. Over…
DN630 Pipeline Welding & Installation Project – Queensland
National Pump & Energy (NPE) was engaged to deliver specialised support for a DN630 HDPE pipeline installation as part of…
Poly Butt Welding for Resource Recovery Park
National Pump & Energy (NPE) was engaged to supply experienced poly welders and specialist poly welding equipment to support onsite…



