Power Generation - Project Management

Rio Tinto – Dampier Salt Limited

Remote power generator hire

Power Temporary Sea Water Transfer

NPE provided power for temporary sea water transfer for pond zero, at Rio Tinto’s Dampier Salt Limited.

Sea water transfer of 5,000lt/sec to pond zero salt water evaporation pond whilst permanent pumping system undergoes refurbishment.

Requirements

Sea water transfer of 5,000lt/sec to pond zero salt water evaporation pond whilst permanent pumping system undergoes refurbishment

Equipment

  • 2 x 1250kva gensets
  • 2 x 1500kva 415 – 1000vsubstation
  • 7 x 220KW 1000v soft starters
  • 7 x 220 I000v electric motors
  • 1000mts 241.1 trailing cable
  • 2 x 900mm ultrasonic flow metres
  • Remote monitoring at customer control room and via internet