PSL / Conoco Phillips – Darwin, Northern Territory

Pipeline Pre-commissioning

NPE provided expert services to client PSL/Conoco Phillips to complete the operational pre-commissioning of a pumping system to supply filtered, treated water to pig launcher at 300lt/sec and 25bar at Bayu Undan Gas Pipeline, in the Northern Territory.

Services provided include scope, design, construct and function test pumping package; installation and deployment of all land and marine components; commission and operate complete package; decommission and rehabilitate.

Requirements

Complete operational pre-commissioning pumping system to supply filtered, treated water to pig launcher at 300lt/sec and 25bar at Bayu Undan Gas Pipeline

Equipment

  • Offshore pontoons and anchoring systems
  • Electrically driven suction lift pumps
  • 500kva diesel generators
  • Break Tank with primary filtration screens
  • Rotary self-cleaning filters
  • Chemical dosing pumps
  • 750hp high head, high volume flood pumps
  • Certified flow meters
  • High pressure hose, spools and valves
  • Twin 500m floating HDPE pipelines
  • Complete site power and lighting

National Pump & Energy have the people, products and expertise to deliver on your project needs. For more information contact us today.