NPE installed 42km pipe work, refurbished existing pump station and installed a new pump station for Black Swan Nickel at the Avalon Borefield Pipeline.
Works Included
- Pressure testing 42kms of pipe
- Tie into existing tailings and return infrastructure
- Retrieval and relocation of 9,000m x 355mm pipe work 400km to site
- Refurbishment of existing Borefield pump station, replacing pumps and spooling in HDPE
- Installation of new booster station pumps and pipe work in HDPE
- Installation and commissioning of Bores